[2019]DLSC6584 • July 24, 2019 • Supreme Court
TIESO GHANA LIMITED vs. EUROGET DE-INVESTA SA
KOTEY, JSC:- Before us is an appeal from the judgment of the Court of Appeal affirming a decision on the trial High Court dismissing an application by the Plaintiff/ Appellant/Appellant (hereinafter Plaintiff) for leave to enter final judgment under Order 64, Rule 13 of C.I. 47. The Plaintiff was a subcontractor of the Defendant/Respondent/Respondent (hereinafter Defendant) for the construction of a 160-bed regional hospital at Wa in the Upper West region. Their contract was governed by “Federation Internationale Des Ingenieurs-Conseils”, International Federation of Consulting Engineers Rules (hereinafter referred to as FIDIC Rules) which contain dispute resolution provisions. For ease of reference we reproduce the dispute resolution provisions of the FIDIC Rules. “20.1 Contractor’s Claim If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in con...